Remove effort estimates from implementation phases document
Strip effort/risk columns from task tables and remove the §6.9 Effort Summary section with its pie chart and resource requirements table. Renumber §6.10 Quick Wins → §6.9. Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
This commit is contained in:
@@ -52,18 +52,16 @@ gantt
|
||||
|
||||
### Tasks
|
||||
|
||||
| Task | Description | Effort | Risk |
|
||||
| ---- | ----------------------------------------------------- | ------ | ------ |
|
||||
| 1.1 | Add OpenTelemetry C++ SDK to Conan/CMake | 2d | Low |
|
||||
| 1.2 | Implement `Telemetry` interface and factory | 2d | Low |
|
||||
| 1.3 | Implement `SpanGuard` RAII wrapper | 1d | Low |
|
||||
| 1.4 | Implement configuration parser | 1d | Low |
|
||||
| 1.5 | Integrate into `ApplicationImp` | 1d | Medium |
|
||||
| 1.6 | Add conditional compilation (`XRPL_ENABLE_TELEMETRY`) | 1d | Low |
|
||||
| 1.7 | Create `NullTelemetry` no-op implementation | 0.5d | Low |
|
||||
| 1.8 | Unit tests for core infrastructure | 1.5d | Low |
|
||||
|
||||
**Total Effort**: 10 days (2 developers)
|
||||
| Task | Description |
|
||||
| ---- | ----------------------------------------------------- |
|
||||
| 1.1 | Add OpenTelemetry C++ SDK to Conan/CMake |
|
||||
| 1.2 | Implement `Telemetry` interface and factory |
|
||||
| 1.3 | Implement `SpanGuard` RAII wrapper |
|
||||
| 1.4 | Implement configuration parser |
|
||||
| 1.5 | Integrate into `ApplicationImp` |
|
||||
| 1.6 | Add conditional compilation (`XRPL_ENABLE_TELEMETRY`) |
|
||||
| 1.7 | Create `NullTelemetry` no-op implementation |
|
||||
| 1.8 | Unit tests for core infrastructure |
|
||||
|
||||
### Exit Criteria
|
||||
|
||||
@@ -81,18 +79,16 @@ gantt
|
||||
|
||||
### Tasks
|
||||
|
||||
| Task | Description | Effort | Risk |
|
||||
| ---- | -------------------------------------------------- | ------ | ------ |
|
||||
| 2.1 | Implement W3C Trace Context HTTP header extraction | 1d | Low |
|
||||
| 2.2 | Instrument `ServerHandler::onRequest()` | 1d | Low |
|
||||
| 2.3 | Instrument `RPCHandler::doCommand()` | 2d | Medium |
|
||||
| 2.4 | Add RPC-specific attributes | 1d | Low |
|
||||
| 2.5 | Instrument WebSocket handler | 1d | Medium |
|
||||
| 2.6 | Integration tests for RPC tracing | 2d | Low |
|
||||
| 2.7 | Performance benchmarks | 1d | Low |
|
||||
| 2.8 | Documentation | 1d | Low |
|
||||
|
||||
**Total Effort**: 10 days
|
||||
| Task | Description |
|
||||
| ---- | -------------------------------------------------- |
|
||||
| 2.1 | Implement W3C Trace Context HTTP header extraction |
|
||||
| 2.2 | Instrument `ServerHandler::onRequest()` |
|
||||
| 2.3 | Instrument `RPCHandler::doCommand()` |
|
||||
| 2.4 | Add RPC-specific attributes |
|
||||
| 2.5 | Instrument WebSocket handler |
|
||||
| 2.6 | Integration tests for RPC tracing |
|
||||
| 2.7 | Performance benchmarks |
|
||||
| 2.8 | Documentation |
|
||||
|
||||
### Exit Criteria
|
||||
|
||||
@@ -110,18 +106,16 @@ gantt
|
||||
|
||||
### Tasks
|
||||
|
||||
| Task | Description | Effort | Risk |
|
||||
| ---- | --------------------------------------------- | ------ | ------ |
|
||||
| 3.1 | Define `TraceContext` Protocol Buffer message | 1d | Low |
|
||||
| 3.2 | Implement protobuf context serialization | 1d | Low |
|
||||
| 3.3 | Instrument `PeerImp::handleTransaction()` | 2d | Medium |
|
||||
| 3.4 | Instrument `NetworkOPs::submitTransaction()` | 1d | Medium |
|
||||
| 3.5 | Instrument HashRouter integration | 1d | Medium |
|
||||
| 3.6 | Implement relay context propagation | 2d | High |
|
||||
| 3.7 | Integration tests (multi-node) | 2d | Medium |
|
||||
| 3.8 | Performance benchmarks | 1d | Low |
|
||||
|
||||
**Total Effort**: 11 days
|
||||
| Task | Description |
|
||||
| ---- | --------------------------------------------- |
|
||||
| 3.1 | Define `TraceContext` Protocol Buffer message |
|
||||
| 3.2 | Implement protobuf context serialization |
|
||||
| 3.3 | Instrument `PeerImp::handleTransaction()` |
|
||||
| 3.4 | Instrument `NetworkOPs::submitTransaction()` |
|
||||
| 3.5 | Instrument HashRouter integration |
|
||||
| 3.6 | Implement relay context propagation |
|
||||
| 3.7 | Integration tests (multi-node) |
|
||||
| 3.8 | Performance benchmarks |
|
||||
|
||||
### Exit Criteria
|
||||
|
||||
@@ -139,18 +133,16 @@ gantt
|
||||
|
||||
### Tasks
|
||||
|
||||
| Task | Description | Effort | Risk |
|
||||
| ---- | ---------------------------------------------- | ------ | ------ |
|
||||
| 4.1 | Instrument `RCLConsensusAdaptor::startRound()` | 1d | Medium |
|
||||
| 4.2 | Instrument phase transitions | 2d | Medium |
|
||||
| 4.3 | Instrument proposal handling | 2d | High |
|
||||
| 4.4 | Instrument validation handling | 1d | Medium |
|
||||
| 4.5 | Add consensus-specific attributes | 1d | Low |
|
||||
| 4.6 | Correlate with transaction traces | 1d | Medium |
|
||||
| 4.7 | Multi-validator integration tests | 2d | High |
|
||||
| 4.8 | Performance validation | 1d | Medium |
|
||||
|
||||
**Total Effort**: 11 days
|
||||
| Task | Description |
|
||||
| ---- | ---------------------------------------------- |
|
||||
| 4.1 | Instrument `RCLConsensusAdaptor::startRound()` |
|
||||
| 4.2 | Instrument phase transitions |
|
||||
| 4.3 | Instrument proposal handling |
|
||||
| 4.4 | Instrument validation handling |
|
||||
| 4.5 | Add consensus-specific attributes |
|
||||
| 4.6 | Correlate with transaction traces |
|
||||
| 4.7 | Multi-validator integration tests |
|
||||
| 4.8 | Performance validation |
|
||||
|
||||
### Exit Criteria
|
||||
|
||||
@@ -187,17 +179,15 @@ See [Phase4_taskList.md](./Phase4_taskList.md) for the full spec and implementat
|
||||
|
||||
### Tasks
|
||||
|
||||
| Task | Description | Effort | Risk |
|
||||
| ---- | ----------------------------- | ------ | ---- |
|
||||
| 5.1 | Operator runbook | 1d | Low |
|
||||
| 5.2 | Grafana dashboards | 1d | Low |
|
||||
| 5.3 | Alert definitions | 0.5d | Low |
|
||||
| 5.4 | Collector deployment examples | 0.5d | Low |
|
||||
| 5.5 | Developer documentation | 1d | Low |
|
||||
| 5.6 | Training materials | 0.5d | Low |
|
||||
| 5.7 | Final integration testing | 0.5d | Low |
|
||||
|
||||
**Total Effort**: 5 days
|
||||
| Task | Description |
|
||||
| ---- | ----------------------------- |
|
||||
| 5.1 | Operator runbook |
|
||||
| 5.2 | Grafana dashboards |
|
||||
| 5.3 | Alert definitions |
|
||||
| 5.4 | Collector deployment examples |
|
||||
| 5.5 | Developer documentation |
|
||||
| 5.6 | Training materials |
|
||||
| 5.7 | Final integration testing |
|
||||
|
||||
---
|
||||
|
||||
@@ -245,42 +235,11 @@ quadrantChart
|
||||
|
||||
---
|
||||
|
||||
## 6.9 Effort Summary
|
||||
|
||||
<div align="center">
|
||||
|
||||
```mermaid
|
||||
%%{init: {'pie': {'textPosition': 0.75}}}%%
|
||||
pie showData
|
||||
"Phase 1: Core Infrastructure" : 10
|
||||
"Phase 2: RPC Tracing" : 10
|
||||
"Phase 3: Transaction Tracing" : 11
|
||||
"Phase 4: Consensus Tracing" : 11
|
||||
"Phase 5: Documentation" : 5
|
||||
```
|
||||
|
||||
**Total Effort Distribution (47 developer-days)**
|
||||
|
||||
</div>
|
||||
|
||||
### Resource Requirements
|
||||
|
||||
| Phase | Developers | Duration | Total Effort |
|
||||
| --------- | ---------- | ----------- | ------------ |
|
||||
| 1 | 2 | 2 weeks | 10 days |
|
||||
| 2 | 1-2 | 2 weeks | 10 days |
|
||||
| 3 | 2 | 2 weeks | 11 days |
|
||||
| 4 | 2 | 2 weeks | 11 days |
|
||||
| 5 | 1 | 1 week | 5 days |
|
||||
| **Total** | **2** | **9 weeks** | **47 days** |
|
||||
|
||||
---
|
||||
|
||||
## 6.10 Quick Wins and Crawl-Walk-Run Strategy
|
||||
## 6.9 Quick Wins and Crawl-Walk-Run Strategy
|
||||
|
||||
This section outlines a prioritized approach to maximize ROI with minimal initial investment.
|
||||
|
||||
### 6.10.1 Crawl-Walk-Run Overview
|
||||
### 6.9.1 Crawl-Walk-Run Overview
|
||||
|
||||
<div align="center">
|
||||
|
||||
@@ -319,17 +278,17 @@ flowchart TB
|
||||
|
||||
</div>
|
||||
|
||||
### 6.10.2 Quick Wins (Immediate Value)
|
||||
### 6.9.2 Quick Wins (Immediate Value)
|
||||
|
||||
| Quick Win | Effort | Value | When to Deploy |
|
||||
| ------------------------------ | -------- | ------ | -------------- |
|
||||
| **RPC Command Tracing** | 2 days | High | Week 2 |
|
||||
| **RPC Latency Histograms** | 0.5 days | High | Week 2 |
|
||||
| **Error Rate Dashboard** | 0.5 days | Medium | Week 2 |
|
||||
| **Transaction Submit Tracing** | 1 day | High | Week 3 |
|
||||
| **Consensus Round Duration** | 1 day | Medium | Week 6 |
|
||||
| Quick Win | Value | When to Deploy |
|
||||
| ------------------------------ | ------ | -------------- |
|
||||
| **RPC Command Tracing** | High | Week 2 |
|
||||
| **RPC Latency Histograms** | High | Week 2 |
|
||||
| **Error Rate Dashboard** | Medium | Week 2 |
|
||||
| **Transaction Submit Tracing** | High | Week 3 |
|
||||
| **Consensus Round Duration** | Medium | Week 6 |
|
||||
|
||||
### 6.10.3 CRAWL Phase (Weeks 1-2)
|
||||
### 6.9.3 CRAWL Phase (Weeks 1-2)
|
||||
|
||||
**Goal**: Get basic tracing working with minimal code changes.
|
||||
|
||||
@@ -349,7 +308,7 @@ flowchart TB
|
||||
- No cross-node complexity
|
||||
- Single file modification to existing code
|
||||
|
||||
### 6.10.4 WALK Phase (Weeks 3-5)
|
||||
### 6.9.4 WALK Phase (Weeks 3-5)
|
||||
|
||||
**Goal**: Add transaction lifecycle tracing across nodes.
|
||||
|
||||
@@ -368,7 +327,7 @@ flowchart TB
|
||||
- Moderate complexity (requires context propagation)
|
||||
- High value for debugging transaction issues
|
||||
|
||||
### 6.10.5 RUN Phase (Weeks 6-9)
|
||||
### 6.9.5 RUN Phase (Weeks 6-9)
|
||||
|
||||
**Goal**: Full observability including consensus.
|
||||
|
||||
@@ -387,7 +346,7 @@ flowchart TB
|
||||
- Requires thorough testing
|
||||
- Lower relative value (consensus issues are rarer)
|
||||
|
||||
### 6.10.6 ROI Prioritization Matrix
|
||||
### 6.9.6 ROI Prioritization Matrix
|
||||
|
||||
```mermaid
|
||||
quadrantChart
|
||||
|
||||