@@ -188,14 +188,14 @@ SHAMap tracing are not implemented.
### Spans Produced
| Span Name | Location | Attributes |
| --------------------------- | ---------------------- | --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- |
| `consensus.phase.open` | `Consensus.h:707` | _(none)_ |
| `consensus.proposal.send` | `RCLConsensus.cpp:232` | `xrpl.consensus.round` |
| `consensus.ledger_close` | `RCLConsensus.cpp:341` | `xrpl.consensus.ledger.seq`, `xrpl.consensus.mode` |
| `consensus.accept` | `RCLConsensus.cpp:492` | `xrpl.consensus.proposers`, `xrpl.consensus.round_time_ms`, `xrpl.consensus.quorum` |
| `consensus.accept.apply` | `RCLConsensus.cpp:541` | `xrpl.consensus.close_time`, `close_time_correct`, `close_resolution_ms`, `state`, `proposing`, `round_time_ms`, `ledger.seq`, `parent_close_time`, `close_time_self`, `close_time_vote_bins`, `resolution_direction` |
| `consensus.validation.send` | `RCLConsensus.cpp:900` | `xrpl.consensus.ledger.seq`, `xrpl.consensus.proposing` |
| Span Name | Location | Attributes |
| --------------------------- | ------------------ | --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- |
| `consensus.phase.open` | `Consensus.h` | _(none)_ |
| `consensus.proposal.send` | `RCLConsensus.cpp` | `xrpl.consensus.round` |
| `consensus.ledger_close` | `RCLConsensus.cpp` | `xrpl.consensus.ledger.seq`, `xrpl.consensus.mode` |
| `consensus.accept` | `RCLConsensus.cpp` | `xrpl.consensus.proposers`, `xrpl.consensus.round_time_ms`, `xrpl.consensus.quorum` |
| `consensus.accept.apply` | `RCLConsensus.cpp` | `xrpl.consensus.close_time`, `close_time_correct`, `close_resolution_ms`, `state`, `proposing`, `round_time_ms`, `ledger.seq`, `parent_close_time`, `close_time_self`, `close_time_vote_bins`, `resolution_direction` |
| `consensus.validation.send` | `RCLConsensus.cpp` | `xrpl.consensus.ledger.seq`, `xrpl.consensus.proposing` |
### Exit Criteria
@@ -216,8 +216,7 @@ Phase 4a (establish-phase gap fill & cross-node correlation) adds:
in the same round share the same `trace_id` (switchable via
`consensus_trace_strategy` config: `"deterministic"` or `"attribute"`).
See [Configuration Reference](./05-configuration-reference.md) for full
configuration options. The `consensus_trace_strategy` option will be
documented in the configuration reference as part of Phase 4a implementation.
configuration options.
- **Round lifecycle spans**: `consensus.round` with round-to-round span links.
- **Establish phase**: `consensus.establish`, `consensus.update_positions` (with
`dispute.resolve` events), `consensus.check` (with threshold tracking).
@@ -360,7 +359,7 @@ xrpld has a mature metrics framework (`beast::insight`) that emits StatsD-format
### Wire Format Fix (Task 6.1) — DEFERRED
The `StatsDMeterImpl` in `StatsDCollector.cpp:706` sends metrics with `|m` suffix, which is non-standard StatsD. The OTel StatsD receiver silently drops these. Fix: change `|m` to `|c` (counter), which is semantically correct since meters are increment-only counters. Only 2 metrics are affected (`warn`, `drop` in Resource Manager).
The `StatsDMeterImpl` in `StatsDCollector.cpp` sends metrics with `|m` suffix, which is non-standard StatsD. The OTel StatsD receiver silently drops these. Fix: change `|m` to `|c` (counter), which is semantically correct since meters are increment-only counters. Only 2 metrics are affected (`warn`, `drop` in Resource Manager).
**Status**: Deferred as a separate change this is a breaking change for any StatsD backend that previously consumed the custom `|m` type. The Resource Warnings and Resource Drops dashboard panels will show no data until this fix is applied.
@@ -719,13 +718,13 @@ quadrantChart
---
## 6.9 Quick Wins and Crawl-Walk-Run Strategy
## 6.11 Quick Wins and Crawl-Walk-Run Strategy
> **TxQ** = Transaction Queue
This section outlines a prioritized approach to maximize ROI with minimal initial investment.
### 6.9.1 Crawl-Walk-Run Overview
### 6.11.1 Crawl-Walk-Run Overview
<div align="center">
@@ -774,7 +773,7 @@ flowchart TB
- **RUN (Weeks 6-9)**: Full consensus instrumentation, establish-phase gap fill, cross-node correlation, StatsD integration, and production deployment with sampling and alerting.
- **Arrows (crawl → walk → run)**: Each phase builds on the prior one; you cannot skip ahead because later phases depend on infrastructure established earlier.
### 6.9.2 Quick Wins (Immediate Value)
### 6.11.2 Quick Wins (Immediate Value)
| Quick Win | Value | When to Deploy |
| ------------------------------ | ------ | -------------- |
@@ -784,7 +783,7 @@ flowchart TB
| **Transaction Submit Tracing** | High | Week 3 |
| **Consensus Round Duration** | Medium | Week 6 |
### 6.9.3 CRAWL Phase (Weeks 1-2)
### 6.11.3 CRAWL Phase (Weeks 1-2)
**Goal**: Get basic tracing working with minimal code changes.
@@ -806,7 +805,7 @@ flowchart TB
- No cross-node complexity
- Single file modification to existing code
### 6.9.4 WALK Phase (Weeks 3-5)
### 6.11.4 WALK Phase (Weeks 3-5)
**Goal**: Add transaction lifecycle tracing across nodes.
@@ -827,7 +826,7 @@ flowchart TB
- Moderate complexity (requires context propagation)
- High value for debugging transaction issues
### 6.9.5 RUN Phase (Weeks 6-9)
### 6.11.5 RUN Phase (Weeks 6-9)
**Goal**: Full observability including consensus.
@@ -850,7 +849,7 @@ flowchart TB
- Requires thorough testing
- Lower relative value (consensus issues are rarer)
### 6.9.6 ROI Prioritization Matrix
### 6.11.6 ROI Prioritization Matrix
```mermaid
quadrantChart
@@ -872,13 +871,13 @@ quadrantChart
---
## 6.13 Definition of Done
## 6.12 Definition of Done
> **TxQ** = Transaction Queue | **HA** = High Availability
Clear, measurable criteria for each phase.
### 6.13.1 Phase 1: Core Infrastructure
### 6.12.1 Phase 1: Core Infrastructure
| Criterion | Measurement | Target |
| --------------- | ---------------------------------------------------------- | ---------------------------- |
@@ -890,7 +889,7 @@ Clear, measurable criteria for each phase.
**Definition of Done**: All criteria met, PR merged, no regressions in CI.
### 6.13.2 Phase 2: RPC Tracing
### 6.12.2 Phase 2: RPC Tracing
| Criterion | Measurement | Target |
| ------------------ | ---------------------------------- | -------------------------- |
@@ -902,7 +901,7 @@ Clear, measurable criteria for each phase.
**Definition of Done**: RPC traces visible in Tempo for all commands, dashboard shows latency distribution.
### 6.13.3 Phase 3: Transaction Tracing
### 6.12.3 Phase 3: Transaction Tracing
| Criterion | Measurement | Target |
| --------------------- | ------------------------------------------------- | -------------------------------------------------------- |
@@ -917,7 +916,7 @@ Clear, measurable criteria for each phase.
**Definition of Done**: Transaction traces span 3+ nodes in test network with deterministic trace_id correlation, parent-child ordering via protobuf propagation, and performance within bounds.
### 6.13.4 Phase 4: Consensus Tracing
### 6.12.4 Phase 4: Consensus Tracing
| Criterion | Measurement | Target |
| -------------------- | ----------------------------- | ------------------------- |
@@ -929,7 +928,7 @@ Clear, measurable criteria for each phase.
**Definition of Done**: Consensus rounds fully traceable, no impact on consensus timing.
### 6.13.5 Phase 5: Production Deployment
### 6.12.5 Phase 5: Production Deployment
| Criterion | Measurement | Target |
| ------------ | ---------------------------- | -------------------------- |
@@ -942,7 +941,7 @@ Clear, measurable criteria for each phase.
**Definition of Done**: Telemetry running in production, operators trained, alerts active.
### 6.13.6 Success Metrics Summary
### 6.12.6 Success Metrics Summary
| Phase | Primary Metric | Secondary Metric | Deadline |
| ------- | ---------------------------- | --------------------------- | -------------- |
@@ -957,7 +956,7 @@ Clear, measurable criteria for each phase.
---
## 6.14 Recommended Implementation Order
## 6.13 Recommended Implementation Order
Based on ROI analysis, implement in this exact order: